This electrical capacity is spread within four farms covering five Pas‑de‑Calais districts –Fauquembergues, Renty, Audincthun, Reclinghem and Vincly – with an installed capacity of between 7.5 and 12 MW. Commissioned in October 2004, these farms are characterised by an excellent level of production, confirmed by the first years of operation.
Farm | Installed capacity (MW) | Number of turbines (1.5 MW) |
Fauquembergues | 12 | 8 |
Renty Audincthun | 7.5 | 5 |
Reclinghem | 9 | 6 |
Vincly | 9 | 6 |
TOTAL | 37.5 | 25 |
Thanks to this acquisition, Gaz de France is continuing to develop its wind power production. In this way, the Group will have a total installed capacity of nearly 120 MW by the end of 2007 and 145 MW at the start of 2008, with the new farms that are currently under construction being brought into service.
This acquisition is in line with Gaz de France's sustainable development policy, working to reduce greenhouse gas emissions and develop the use of renewable energies in order to combat global warming. Gaz de France's wind power production will hence be the most important in
Group profile:
The Gaz de France group is a major player in the European energy market. Ranked first for the distribution of natural gas in
Press Contact:
Financial Communication Contact:
Armelle Dillar
Tel: +33 1 47 54 30 17
E-mail : armelle.dillar@gazdefrance.com
Financial Communication Contact:
Brigitte Roeser Herlin
Tel.: +33 1 47 54 77 25
E-mail: GDF-IR-TEAM@gazdefrance.com
2007 Annual Report
2007 Registration document
2007 Sustainable Development Report
Gaz de France and Sustainable Development in 2007
Communication on progress 2006